Energy Recovery Facility

New Tensioned Membrane Mesh

Project Outline

Base Structures were asked to tender for the fitting of a screen to minimize and soften the industrial visual impact of the cooling section built at the rounded northern end of the new £140 million Energy Recovery Facility (ERF). When operational this new ERF will take receipt of some 210,000 tonnes of municipal solid waste each year, to be treated in two boilers. The challenge to Base Structures was to install a suitable screening for the air-cooled condenser area: a 54 m diameter half dome on the northern end of the Newhaven ERF which needed to obfuscate the harsh detail of the externally mounted cooling equipment.

 

 

Energy Recovery Facility

Our Solution

“We hit upon the idea of a ‘wavy’ clamping system,” says Base Structures’ Head of Projects, Mark Smith, “using an aluminium extrusion which allowed us to pass the load evenly through the steel, rather than through the PVC. We made a series of different prototypes until we evolved a fully engineered design that achieved the loads necessary.”

Two different clamps were developed: an ‘intermediate’ design to hold the sections of fabric together, and a ‘perimeter’ design, used to clamp the joined sections to the supporting steel structure. The only modification necessary was to pre-stress the mesh before it was clamped in.

Installation of the mesh above the heavy process equipment took around six weeks for a team of six on the ground fitting sections together and 14 riggers, clamping and bolting the sections into place. Having refined this techique, Base Structures is confident it will significantly reduce this build time for future projects.

Results

“Base Structures found a technical solution on the basis of their knowledge, creativity and problem solving attitude. They transferred successfully the information from design study onto the final construction.”
Andreas Clausen, HOCHTIEF Construction Manager

Newhaven energy recovery facility tensioned mesh
Newhaven energy recovery facility PVC mesh
Newhaven energy recovery facility fabric cladding
Newhaven energy recovery facility PVC mesh

Project Summary

Client
Veolia
Location
East Sussex
Date
2011
Architect
S'Pace
Contractor
Hochtief
Fabric
PVC Mesh
Product
Fabric Cladding
Services
Design
Design
Project Management
Project Management
Manufacturing
Manufacturing
Installation
Installation
Maintenance